Sample project with illustrative data.

Hunter Data Center Project

Progress & payments

5 packages · updated Nov 23, 2026

Package
Verified complete
59.8%5.6% behind target
1,717 of 2,870 assetsTarget today 65.4%
Forecast finish
Feb 13, 2027
13 days after PC (Feb 1, 2027)
Set by the slowest package: SC-04 BMS & controls
Critical path
245 / 411
166 still open
Blocked
25
Assets with an open blocking record, such as an NCR
Claimable now
$620K
of $4.8M in milestones

Verified progress · Hunter Data Center Project

Assets with evidence linked and nothing blocking, week by week. Rebuilt from the evidence audit trail, back to day one.

VerifiedTargetForecast at the 4-week rateScope (asset register)PC date◆ Milestone due date

Target is the sum of every package’s straight line from its first asset upload to its PC date.

Show the numbers
WeekVerifiedTargetScopeCritical path openBlocked
Today (Nov 23)1,7171,8762,87016625
Nov 231,7021,8662,87016825
Nov 161,5591,7422,87018414
Nov 91,4111,6192,87021010
Nov 21,2091,4952,8702302
Oct 261,0211,3722,8702611
Oct 198671,2322,8032802
Oct 127401,1052,7812982
Oct 55059862,7803352
Sep 283228412,7173523
Sep 212467242,7163703
Sep 141806082,1573181
Sep 71395072,1013172
Aug 311014211,8112633
Aug 24763501,8102661
Aug 17422621,7152601
Aug 10251951,7142621
Aug 3111281,2851700
Jul 274801,0811510
Jul 202401,0801510
Jul 1300100

Critical path and blocking

Open critical-path assets have to reach zero by PC. The dashed line is the burn-down needed from today.

Critical path openBlocked assetsNeeded burn-down

Assets verified per week

Speeding up or stalling, against the rate needed to make PC.

Verified that week4-week average: 171/wkNeeded to make PC: 116/wk

Where it's behind

Verified against today’s target, most behind first. The dark tick marks the target.

PackageVerifiedProgress vs target%Gap
SC-02 Mechanical & HVAC9 blocked289 / 48659.5%−13.7%
SC-04 BMS & controls8 blocked238 / 62837.9%−12.5%
SC-01 HV & LV electrical6 blocked804 / 1,24064.8%−5.9%
SC-03 Fire protection2 blocked204 / 31265.4%+1.8%
SC-05 Hydraulics182 / 20489.2%+25.9%

59.8% verified as of Nov 23, 2026. Blocking status uses each package's current label settings.

Field app

The same sample project, on site.

The Holdpoint iPhone app works from the packages saved on the phone, with or without signal. Everything recorded on site syncs back to the project.

  1. Your packages screen in the Holdpoint field app

    1Your packages

  2. Package, offline screen in the Holdpoint field app

    2Package, offline

  3. Scan a tag screen in the Holdpoint field app

    3Scan a tag

  4. Check sheet screen in the Holdpoint field app

    4Check sheet

  5. Sign off screen in the Holdpoint field app

    5Sign off

  6. Photo to ITR screen in the Holdpoint field app

    6Photo to ITR

  7. Sync queue screen in the Holdpoint field app

    7Sync queue

A 25-minute walkthrough with Holdpoint's CEO and Founder, on your project structure: packages, assets, criteria and evidence.

Book a walkthrough