Sample project with illustrative data.

Hunter Data Center Project

Progress & payments

5 packages · updated Oct 8, 2026

Package
Verified complete
62.3%5.0% behind target
1,789 of 2,870 assetsTarget today 67.4%
Forecast finish
Dec 26, 2026
12 days after PC (Dec 14, 2026)
Set by the slowest package: SC-04 BMS & controls
Critical path
259 / 411
152 still open
Blocked
25
Assets with an open blocking record, such as an NCR
Claimable now
$620K
of $4.8M in milestones

Verified progress · Hunter Data Center Project

Assets with evidence linked and nothing blocking, week by week. Rebuilt from the evidence audit trail, back to day one.

VerifiedTargetForecast at the 4-week rateScope (asset register)PC date◆ Milestone due date

Target is the sum of every package’s straight line from its first asset upload to its PC date.

Show the numbers
WeekVerifiedTargetScopeCritical path openBlocked
Today (Oct 8)1,7891,9332,87015225
Oct 51,7061,8662,87016819
Sep 281,5601,7422,87018410
Sep 211,4111,6192,8702108
Sep 141,2101,4952,8702301
Sep 71,0211,3722,8702611
Aug 318671,2322,8032802
Aug 247401,1052,7812982
Aug 175059862,7803352
Aug 103228412,7173523
Aug 32467242,7163703
Jul 271806082,1573181
Jul 201395072,1013172
Jul 131014211,8112633
Jul 6763501,8102661
Jun 29422621,7152601
Jun 22251951,7142621
Jun 15111281,2851700
Jun 84801,0811510
Jun 12401,0801510
May 2500100

Critical path and blocking

Open critical-path assets have to reach zero by PC. The dashed line is the burn-down needed from today.

Critical path openBlocked assetsNeeded burn-down

Assets verified per week

Speeding up or stalling, against the rate needed to make PC.

Verified that week4-week average: 167/wkNeeded to make PC: 114/wk

Where it's behind

Verified against today’s target, most behind first. The dark tick marks the target.

PackageVerifiedProgress vs target%Gap
SC-04 BMS & controls8 blocked249 / 62839.6%−13.1%
SC-02 Mechanical & HVAC9 blocked307 / 48663.2%−12.1%
SC-01 HV & LV electrical6 blocked833 / 1,24067.2%−5.2%
SC-03 Fire protection2 blocked216 / 31269.2%+3.2%
SC-05 Hydraulics184 / 20490.2%+25.2%

62.3% verified as of Oct 8, 2026. Blocking status uses each package's current label settings.

A 25-minute walkthrough with Holdpoint's CEO and Founder, on your project structure: packages, assets, criteria and evidence.

Book a walkthrough